Projects Completed
Design & Construction of RCC U.G Sump, ESR
44
including providing & Laying of Rising Mains,
Distribution Network, Pumping M/C and Allied works
for Augmentation of Water Supply Under Infrastructure
Development Scheme for small and Medium Town
Project. BALASINOR NAGARPALIKA BALASINOR.
CLIENT
Balasinor Nagar Palika, Balasinor.
STARTING DATE 13.02.2009
COMPLETION DATE Work in progress
STRUCTURAL DETAILS
(a) Foundation Pipe line : 2800 m.
( b) Superstructure Overhead water tank: - 6.5 lakh Lit.
U/G Sump: 12 Lakh Lit.